[vc_row full_width=”stretch_row_content_no_spaces” css=”.vc_custom_1518033741450{margin-right: 0px !important;margin-left: 0px !important;padding-right: 0px !important;padding-left: 0px !important;}”][vc_column css=”.vc_custom_1518033832120{margin-right: 0px !important;margin-left: 0px !important;padding-right: 0px !important;padding-left: 0px !important;}”][vc_single_image image=”3006″ img_size=”1600×384″ css=”.vc_custom_1521552857344{margin-top: 0px !important;margin-right: 0px !important;margin-bottom: 0px !important;margin-left: 0px !important;padding-top: 0px !important;padding-right: 0px !important;padding-bottom: 0px !important;padding-left: 0px !important;}”][/vc_column][/vc_row][vc_row css=”.vc_custom_1518033360740{padding-top: 30px !important;padding-bottom: 30px !important;}”][vc_column width=”3/4″][vc_column_text]

Qatar Research and Development Complex

The new 430,000 M2 Qatar Research and Development Complex is part of the Qatar Foundation for Education, Science and Community Development. The new project includes seven main huge and sophisticated research labs, a high bay, and about 210 individual researches offices distrusted.There is a total of more than 1300 lab equipment for very sophisticated researches.[/vc_column_text][/vc_column][vc_column width=”1/4″][vc_single_image image=”3008″ img_size=”full”][/vc_column][/vc_row][vc_row full_width=”stretch_row” css=”.vc_custom_1518034053666{background-color: #eaeaea !important;}”][vc_column][vc_column_text]

Project Details

[/vc_column_text][vc_row_inner][vc_column_inner width=”1/3″][vc_column_text]Project Title:
Qatar Research and Development Complex[/vc_column_text][vc_column_text]Client:
Qatar Foundation [/vc_column_text][/vc_column_inner][vc_column_inner width=”1/3″][vc_column_text]Project Location:
Doha – Qatar[/vc_column_text][vc_column_text]Consultant:[/vc_column_text][/vc_column_inner][vc_column_inner width=”1/3″][vc_column_text]Project Type:
Research Laboratories[/vc_column_text][vc_column_text]Project Date:
2014-2016[/vc_column_text][/vc_column_inner][/vc_row_inner][/vc_column][/vc_row][vc_row][vc_column][vc_column_text]

Our Scope

[/vc_column_text][vc_row_inner][vc_column_inner width=”2/3″][vc_column_text]Hazardous Extract Fans- MK Plastics, Canada

11 Fans arranged as 10+1 arrangement, were installed to extract hazardous air from the building. Each fan with 28,392CFM Capacity to serve the needs of the building sections..

Each fan set is installed on spring vibration isolators and each fan is equipped with isolation damper & Piezometer flow ring.[/vc_column_text][/vc_column_inner][vc_column_inner width=”1/3″][/vc_column_inner][/vc_row_inner][vc_row_inner][vc_column_inner width=”2/3″][vc_column_text]Radio-Isotope Extract Fans- MK Plastics, Canada

2 Fans arranged as 1+1 arrangement, were installed to serve the radio-isotope hazardous air from the building. Each fan with 595CFM Capacity to serve the needs of the building sections. All fans are AMCA certified.

Each fan set is installed on spring vibration isolators and each fan is equipped with isolation damper & Piezometer flow ring.[/vc_column_text][/vc_column_inner][vc_column_inner width=”1/3″][/vc_column_inner][/vc_row_inner][vc_row_inner][vc_column_inner width=”2/3″][vc_column_text]Acid Extract Fans- MK Plastics, Canada

2 Fans arranged as 1+1 arrangement, were installed to serve the Acid Contaminated hazardous air from the building. Each fan with 595CFM Capacity to serve the needs of the building sections. All fans are AMCA certified.

Each fan set is installed on spring vibration isolators and each fan is equipped with isolation damper & Piezometer flow ring.

 

Climasys provided a continues support to all other parties in the project to make sure that the project is fully operational, from the design review with the consultants ending to the system handing-over & training.[/vc_column_text][/vc_column_inner][vc_column_inner width=”1/3″][/vc_column_inner][/vc_row_inner][/vc_column][/vc_row][vc_row][vc_column width=”1/3″][vc_single_image image=”3041″ img_size=”medium” alignment=”right” onclick=”link_image”][/vc_column][vc_column width=”1/3″][vc_single_image image=”3040″ img_size=”medium” alignment=”center” onclick=”link_image”][/vc_column][vc_column width=”1/3″][vc_single_image image=”3065″ img_size=”medium” onclick=”link_image”][/vc_column][/vc_row]